09/01/2010

01:00 PM Feature #149 (New): Add support for multi-row selection in the tree
Support for multi-row selection in the tree to be able to bulk move tasks up and down in the tree or in-/outdent (whe... Robert Ivens

08/31/2010

03:02 PM Feature #147 (New): Add support for assigning resources on a task
Support for assigning resources on a task Robert Ivens
03:01 PM Feature #146 (New): Add support for dependencies on tasks
Add support for the following dependency types:
- start to start
- finish to start
- finish to finish
Robert Ivens
11:27 AM Feature #145 (Closed): Make the gantt (also?) work in hours instead of (only) days
It would be nice if the Gantt would work in hours so that a task can have a duration of lets say 27 hours. Robert Ivens
 